Risks
Each has a date or an action against it. None of them is code.
The team may be too small
Nothing yet shows the team can finish by 31 Dec.
What we do
The capacity estimate on 25 Nov. If it fails, the dates move.
Real pages may arrive late
The Cambridge proof needs real pages for 4 Dec.
What we do
If they have not arrived by 20 Nov, we tell Cambridge that day and move the date.
The launch gates are not ready
A security test of the new platform is to be booked this week. Consent and safeguarding are not specified.
What we do
Book a test of the new platform that reports before 18 Dec, and name the safeguarding lead, this week.
Real marking is not connected
Marks are made up until a real model runs in Sydney.
What we do
Ask for GPU capacity in Sydney now, and settle the rule on outside AI models.
If a gate is still open on 18 Dec, schools stay on today’s platform. Nobody is switched off.